* Admissibility date reflects the date the case was officially registered. All other dates pertain to the date in which a stage was completed.
Case Description
Complaint
On 27 January 2017, residents from the Nakra community (Upper Svaneti region, Georgia), with the support and assistance of the environmental civil society organisation "Green Alternative", brought a complaint to the EIB Complaints Mechanism (EIB-CM). The complaint raises concerns over inadequate assessment of natural geological hazards in connection with the Nenskra HPP project.
EIB-CM Action
Following a preliminary review of the case, the EIB-CM has taken note that the EIB operational team has not finalised the due diligence of the project and that the EIB Management Committee has not taken yet a decision to finance it. In this context, the complaint has been transferred to the Bank’s operational services.