Reference: 20170353
Release date: 23 May 2018

Promoter – Financial Intermediary

PKP POLSKIE LINIE KOLEJOWE SA

Location

Description

The project consists of the deployment of the Global System for Mobile Communications – Railway (GSM-R) – a European Rail Traffic Management System (ERTMS) telecommunications component – and fixed telecommunications over around 13 600 km of the Polish national railway network.

Objectives

The project will contribute to the interoperability of the Polish railway network, bringing it into conformity with the requirements set out in the Trans-European Transport Network (TEN-T) Regulation 1315/2013. This is expected to improve competitiveness of rail vis-à-vis other modes, thereby enhance sustainable transport in line with EU objectives and present environmental and safety benefits due to modal shift from road to rail.

Sector(s)

Proposed EIB finance (Approximate amount)

EUR 250 million

Total cost (Approximate amount)

EUR 570 million

Environmental aspects

The project does not fall in the Environmental Impact Assessment (EIA) Directive. The project will be implemented on around 2 000 sites, where GSM-R antennae masts will be erected. Because of radio coverage reasons, some of these sites may need to be implemented within or close to protected areas. The project's potential impacts on protected areas and species, in accordance with the Habitats Directive and Birds Directive will be appraised.

Procurement

The Bank will require the promoter to ensure that contracts for the implementation of the project have been/will be tendered in accordance with the relevant applicable EU procurement legislation, 2014/25/EU as well as Directive 92/13/EEC as interpreted by the Court of Justice of the EU, with the publication of tender notices in the Official Journal of the European Union, as and where required.

Status

Signed - 30/10/2018

Disclaimer

Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).

Related tags

Poland Transport