Reference: SG/E/2017/53
Received Date: 14 December 2017
Subject: Cairo Metro Line 3 (Phase 3)
Complainant: Confidential
Allegations: Negative social impacts of the financed project. Involuntary resettlement. Housing.
Type: E - Environmental and social impacts of financed projects
Suggestions for improvement: yes
Admissibility*
Assessment*
Investigation*
Dispute Resolution*
Consultation*
Closed*
21/12/2017
7/12/2018
15/04/2020
9/06/2020
24/06/2020
Follow Up*
Closed on 30/09/2022
* Admissibility date reflects the date the case was officially registered. All other dates pertain to the date in which a stage was completed.