Reference: SG/F/2012/01
Received Date: 09 January 2012
Subject: TEŠ - Thermal Power Plant Sostanj
Complainant: FOCUS and Environmental Law Service
Allegations: Mismanagement of the project; alleged failure to comply with national law concerning the profitability of the project
Type: F - Governance aspects of financed operations
Outcome*: Areas for improvement
Suggestions for improvement: yes
Admissibility*
Assessment*
Investigation*
Dispute Resolution*
Consultation*
Closed*
9/01/2012
6/12/2012
3/07/2013
11/10/2013
31/10/2013