Search En menu en ClientConnect
Search
Results
Top 5 search results See all results Advanced search
Top searches
Most visited pages
Reference: SG/E/2018/04
Received Date: 21 January 2018
Subject: Trans Adriatic Pipeline
Complainant: Confidential
Allegations: Alleged negative environmental, social and economic impacts of the project
Type: E - Environmental and social impacts of financed projects
Suggestions for improvement: no
Admissibility*
Assessment*
Investigation*
Dispute Resolution*
Consultation*
Closed*
26/01/2018
27/12/2018
10/03/2020

* Admissibility date reflects the date the case was officially registered. All other dates pertain to the date in which a stage was completed.

Case Description

Complaint  

On 21 January 2018, the EIB Complaints Mechanism (EIB-CM) received a complaint alleging negative environmental, social and economic impacts of the project

 

Project Information