Subject: Trans Adriatic Pipeline
Complainant: Confidential
Allegations: Alleged negative environmental, social and economic impacts of the project, in addition to infringements linked to the implementation of the project
Type: E - Environmental and social impacts of financed projects
Suggestions for improvement: no
Admissibility*
Assessment*
Investigation*
Dispute Resolution*
Consultation*
Closed*
8/02/2018
27/12/2018
10/03/2020

* Admissibility date reflects the date the case was officially registered. All other dates pertain to the date in which a stage was completed.

Case Description

Complaint  

On 5 February 2018, the EIB Complaints Mechanism (EIB-CM) received a complaint alleging negative environmental, social and economic impacts of the project, in addition to infringements linked to the implementation of the project

 

Project Information