Reference: SG/E/2018/19
Received Date: 09 February 2018
Subject: Trans Adriatic Pipeline
Complainant: Confidential
Allegations: Alleged elevated health and safety risks of the project
Type: E - Environmental and social impacts of financed projects
Suggestions for improvement: no
Admissibility*
Assessment*
Investigation*
Dispute Resolution*
Consultation*
Closed*
22/02/2018
27/12/2018
10/03/2020
* Admissibility date reflects the date the case was officially registered. All other dates pertain to the date in which a stage was completed.
Case Description
Complaint
On 9 February 2018, the EIB Complaints Mechanism (EIB-CM) received a complaint alleging elevated health and safety risks of the project, and a request to sign a petition against fossil fuels and the financing of the project