Date de publication: 6 juin 2006
Promoteur – Intermédiaire Financier
Organisation de Mise en valeur du Fleuve Sénégal (OMVS)Lieu
Description
The project consists of construction of a 60 MW run-of-river hydropower plant close to the town of Kayes in Mali. It forms part of the OMVS’s power supply strategy for Mali, Mauritania and Senegal.
Objectifs
The project will make it possible to increase the power generation capacity of Mali, Mauritania and Senegal while limiting costs. This will enable these countries to meet the strongly growing demand for electricity and assist their economic development.
Commentaires
Electricity.
Secteur(s)
Montant BEI envisagé (montant approximatif)
EUR 33 million.
Coût total (montant approximatif)
EUR 102.5 million.
Aspects environnementaux
If the project were to be constructed in the EU, it would fall under Annex II of the EIA Directive (97/11/EC). An Environmental Impact Study has been carried out, including public participation. Taking into account the proposed environmental and social mitigation measures, the overall environmental impact is considered acceptable.
Passation des marchés
The tender process for the turnkey contract is ongoing after publication in the Official Journal on 14 April 2006 of the pre-qualification announcement. Other project components not financed by the Bank follow World Bank procedures, which are in line with the Bank’s Guide to Procurement.
Statut
Signé - 23/11/2006
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).