Date de publication: 9 novembre 2005
Promoteur – Intermédiaire Financier
Cofiroute S.A. (Compagnie Financière et Industrielle des Autoroutes).Lieu
Description
Construction of two sections (63km) of the A85 motorway in the Centre Region of France.
Objectifs
The project will serve to complete the motorway link between the towns of Vierzon and Tours. Connecting the Paris-Clermont-Ferrand A71 motorway to the east and the Anger-Tours section of the A85 motorway (under construction) to the west, the project constitutes an important component of the Nantes – Angers – Tours – Vierzon road, which will link the Atlantic shoreline to the Rhône-Alpes region in south-eastern France and beyond to Switzerland and Italy. The project comes under the Trans-European Transport Network Plan.
Commentaires
Motorways.
Secteur(s)
Montant BEI envisagé (montant approximatif)
Around EUR 200 million.
Coût total (montant approximatif)
Around EUR 550 million.
Aspects environnementaux
The project is covered by EU Directives 85/337/EEC and 92/43/EEC. Its design has been the subject of detailed environmental studies and the motorway has been declared to be in the public interest.
Passation des marchés
The works will be announced by the promoter. The procurement procedures will be examined as part of the project appraisal.
Statut
Signé - 11/07/2006
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).