Recherche Fr menu fr ClientConnect
Recherche
Résultats
5 premiers résultats de la recherche Voir tous les résultats Recherche avancée
Recherches les plus fréquentes
Pages les plus visitées
Référence: 20090674
Date de publication: 16 avril 2010

Promoteur – Intermédiaire Financier

Kenya Electricity Generating Company Ltd. (KenGen)

Lieu

Description

Expansion of existing Olkaria I and new Olkaria IV Geothermal power station to increase generation capacity by a further 280 MW (2x70 MW at each of Olkaria I and IV).

Objectifs

The project will help meet growing electricity demand at a competitive cost and with a limited impact on the environment. Its economic benefits include increased power production, improved security of supply (geothermal power is unaffected by annual hydrological conditions), reduced national dependence on imported fossil fuels for electricity production and additional operational flexibility for existing units at two geothermal power plants.

Secteur(s)

Montant BEI envisagé (montant approximatif)

EUR 120 million.

Coût total (montant approximatif)

EUR 1 007 million.

Aspects environnementaux

An environmental and social impact assessment (ESIA) has been established for both power stations. The studies comprise public consultation and respective monitoring plans. The studies have been approved and respective licenses issued by NEMA (National Environmental Management Authority).

The Olkaria IV part requires resettlement of several Maasai communities. A Resettlement Action Plan (RAP) has been established, which included the participation of the project affected communities. The execution of the RAP will be implemented according to the WB guidelines.

Passation des marchés

Kenyan national law, IDA guidelines (which govern the whole Electricity Expansion Project), EU Directives (2004/17 replacing 93/38) and EIB procurement guidelines require an open tendering procedure with adequate publication for works contracts of this type launched by a public sector company. The promoter will follow these rules and envisages among others a publication of the prequalification notice in the OJEU for the main contracts.

These procurement procedures are in line with the Bank’s procurement guidelines, are considered adequate for the project and satisfactory to the Bank.

Statut

Signé - 15/12/2010

Clause de non-responsabilité

Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

Mots-clés correspondants

Kenya Énergie