Référence: 20100637
Date de publication: 3 octobre 2011

Promoteur – Intermédiaire Financier

Republic of Hungary represented by the National Development Agency

Lieu

Description

The project consists of the modernisation of the existing single track railway line between Sopron-Szombathely-Szentgotthard, 116 km, including installation of new ETCS level 2 signalling system and electrification from Szombathely to Szentgotthard. Purchase of four electric multiple units for regional passenger traffic is also foreseen.

Objectifs

The project aims at increasing railway share in traffic, improving safety and reducing emissions by (i) reducing travel time, (ii) increasing line capacity, (iii) electrification, (iv) improving traffic control, (v) using active and passive noise protection, (vi) installing platforms, lighting and audio visual equipment at stations and stops and (vii) improving or eliminating level crossings.

Commentaires

Under Framework Loan

Secteur(s)

Montant BEI envisagé (montant approximatif)

EUR 15.20 million

Coût total (montant approximatif)

EUR 98 million

Aspects environnementaux

The project falls under Annex II of the EIA Directive and was screened out by the Competent Authorities on the basis of the preliminary environmental impact studies carried out. The Competent Authorities also confirmed that the project will not have any significant impact on declared Natura 2000 sites. Thanks to the electrification of the line, the project will reduce negative environmental externalities due to rail service operation, significantly decreasing associated levels of noise and emission of pollutants. Furthermore, a number of active and passive noise protection measures shall be adopted to minimise potential negative impacts. Compliance with environmental legislations will be verified during appraisal.

Passation des marchés

The project implementation is managed by the GYSEV Zrt. which has obtained in 2006 a 40 year concession for line operation. GYSEV Zrt. Is an Austrian-Hungarian joint venture. The owner of the line is the Hungarian State Treasury represented by the Hungarian State Property Operator Ltd. The company is obliged to comply with the European and National Public Procurement legislation. The procurement process will be verified during appraisal.

Statut

À l'examen - 3/10/2011

Clause de non-responsabilité

Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

Mots-clés correspondants

Hongrie Transports