Date de publication: 2 décembre 2013
Promoteur – Intermédiaire Financier
NATIONAL GRID PLCLieu
Description
Reinforcement and extension of the high-voltage transmission grid in Great Britain, with focus on renewables.
Objectifs
Reinforcement and extension of the high-voltage transmission grid in Great Britain, with focus on renewables.
Secteur(s)
Montant BEI envisagé (montant approximatif)
EUR 1743 million (GBP 1500 million)
Coût total (montant approximatif)
EUR 4002 million (GBP 3445 million)
Aspects environnementaux
Some sub-projects fall under Annex I or Annex II of the EIA Directive 2011/92/EU. The impacts that can be typically expected for the Project relate to visual impact, vegetation clearance, electromagnetic fields, noise nuisance, disturbance during constructions, bird collision/mortality and impact on sea-bed flora and fauna. Environmental impact studies have been carried out as applicable and mitigating and/or compensation measures will be applied as necessary.
Passation des marchés
The Bank will require the Promoter to ensure that contracts for the implementation of the Project are tendered in accordance with the applicable EU procurement legislation (Dir. 2004/17/EC and Dir. 2007/66/EC [amending Directives 1989/665/EEC and 1992/13/EEC]), with publication of tender notices in the EU Official Journal, as and where required.
Statut
Signé - 5/11/2014
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).