Recherche Fr menu fr ClientConnect
Recherche
Résultats
5 premiers résultats de la recherche Voir tous les résultats Recherche avancée
Recherches les plus fréquentes
Pages les plus visitées
Référence: 20110180
Date de publication: 28 août 2013

Promoteur – Intermédiaire Financier

JAVNO PREDUZECE ELEKTROPRIVREDA BOSNE I HERCEGOVINE, the state-owned electricity company in the Federation of Bosnia and Herzegovina.

Lieu

Description

Construction of a 20 MW hydro power plant on the stretch of the river Bosna between the towns of Zenica and Nemila.

Objectifs

The operation will support investments in renewable energy, thus contributing to a sustainable and secure supply of energy and therefore to the long term economic growth and development in BIH. The operation supports the Bank's mandate objectives for Candidate and potential Candidate countries, by promoting renewable energy, tackling climate change and improving security of energy supply.

Commentaires

Secteur(s)

  • Énergie - Production et distribution d'électricité, de gaz, de vapeur et d'air conditionné

Montant BEI envisagé (montant approximatif)

EUR 38 million

Coût total (montant approximatif)

EUR 86 million

Aspects environnementaux

The project falls under Annex II of the EIA Directive 2011/92/EU and it was screened in by national authorities and is subject to an Environmental Impact Assessment. An environmental impact assessment has been performed in accordance with national legislation and it's compliance with EU legislation will be checked during appraisal.

Passation des marchés

The Bank will require the Promoter to ensure that contracts for implementation of the project are tendered in accordance with the applicable EU procurement legislation (Dir 2004/17/EC, 2004/18/EC and Dir. 2007/66/EC), with publication of tender notices in the EU Official Journal, as and where appropriate.

Statut

Signé - 30/06/2014

Clause de non-responsabilité

Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

Mots-clés correspondants

Bosnie-et-Herzégovine Énergie