Recherche Fr menu fr ClientConnect
Recherche
Résultats
5 premiers résultats de la recherche Voir tous les résultats Recherche avancée
Recherches les plus fréquentes
Pages les plus visitées
Référence: 20110247
Date de publication: 28 juillet 2011

Promoteur – Intermédiaire Financier

Enel Green Power S.p.A.

Lieu

Description

Financing of the investment programme of Enel Green Power Romania for the development, construction and operation of three on-shore wind farms located in the regions of Dobrogea (Salbatica and Corugea) and Banat (Moldova Noua) for a total installed capacity of some 260 MW.

Objectifs

The project concerns the development, construction and operation of three Romanian wind farms with a total capacity of 258 MW: Salbatica 1 (70 MW), Salbatica 2 (70 MW), Moldova Noua (48MW) and Corugea (70MW). The projects will be equipped with 126 turbines with a unit capacity ranging from 2.0 to 2.3 MW and hub height between 95 and 101m. Furthermore each project will include the electrical grid to connect the different wind turbines, the civil works for foundations and infrastructure (e.g. access roads) as well as the substation and HV cable for the connection to the network.

Secteur(s)

Montant BEI envisagé (montant approximatif)

EUR 200 million

Coût total (montant approximatif)

EUR 400 million

Aspects environnementaux

The projects fall under Annex II of the EIA Directive 85/337/EC (as amended) and have been screened in by the national competent authorities which have required a full EIA including public consultation. According to the information available all project sites, located in the Dobrogea and Banat regions, may either be inside or close to Natura 2000 sites.  During the appraisal the Bank will check whether the EIAs have been carried out in compliance with the EU Directives and in particular whether the competent environmental authority has performed an appropriate assessment of the impacts (including cumulative ones) of the wind farms on the affected protected natural sites as envisaged under the EU Habitats Directive.

Passation des marchés

Since the promoter is a public undertaking it will follow the EU Procurement Directive 2004/17/EC to procure the equipment and construction works according to the public procurement principles established in the EIB guide to procurement.

Statut

Signé - 28/11/2013

Clause de non-responsabilité

Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

Mots-clés correspondants

Roumanie Énergie