Date de publication: 13 novembre 2012
Promoteur – Intermédiaire Financier
Jordan Wind Project Company PSCLieu
Description
The project comprises the construction and operation of a greenfield wind farm Independent Power Producer (IPP) to produce 117 MW electricity in Jordan. The wind farm will be located in the Tafila Governorate of Jordan, in an area east of the town of Ghurandil and north of the Lafarge Rashidiya cement plant. The electricity generated will be sold to the National Electricity Power Company (NEPCO).
Objectifs
The project will contribute to Jordan's development objective in the energy sector aiming to increase both electricity production and the share of renewable energy in its electricity generation portfolio. It will contribute to climate change mitigation, thereby displacing fossil fuel-based generation and avoiding greenhouse gas emissions. The project also fulfils the government's objective of increasing the participation of the private sector in energy generation.
Commentaires
This operation is covered by the EU Political Risk Guarantee for EIB loans outside the EU.
Secteur(s)
- Énergie - Production et distribution d'électricité, de gaz, de vapeur et d'air conditionné
Montant BEI envisagé (montant approximatif)
EUR 53 million
Coût total (montant approximatif)
EUR 213 million
Aspects environnementaux
The project (including the wind farm connection to the grid) is undergoing an Environmental Impact Assessment (EIA) according to the local legislation which will also include public consultation. No resettlement of local population is envisaged. The project site is located less than 5 km away from the Dana Biosphere Reserve's Eastern border and overlaps with an Important Bird Area. Detailed biodiversity surveys to assess the potential impact on these protected areas and species should be concluded by the end of the year. Compliance with the principles of the EU EIA Directive and the EU Habitats and Birds Directive shall be verified during the appraisal.
Passation des marchés
The promoter has followed a public procurement process for a turn-key Design-Build-Operate-Maintain (DBOM) contract for the wind farm in line with the Bank's procurement guidelines. Contract award and signature is expected for end 2012.
Statut
Signé - 27/11/2013
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).