Description
Conversion of existing Open Cycle Gas Turbine power plant to Combined Cycle Gas Turbine power plant in El Shabab, increasing generating capacity from 1000MW to 1500MW.
Objectifs
The project employs modern, commercially proven, combined-cycle power generation technology to increase the output and fuel efficiency of an existing power plant project. It is expected to contribute to meeting the increasing electricity demand at a competitive cost, with relatively low environmental impact.
Commentaires
This operation is covered by the EU Guarantee for EIB loans outside the EU.
Secteur(s)
Montant BEI envisagé (montant approximatif)
EUR 205 million
Coût total (montant approximatif)
EUR 413 million
Aspects environnementaux
Due to its size and technical characteristics, the project is not required to follow an EIA procedure; however, the EIA for the existing open-cycle power plant, carried out in 2010, will be reviewed during appraisal and any significant gaps in the previous assessment, as well as any social or environmental concerns raised by the conversion to combined-cycle operation, will be required to be addressed by the promoter to the Bank's satisfaction.
Passation des marchés
The project will be required to be procured according to the Banks Guide to Procurement. The procurement process is ongoing.
Statut
Signé - 9/02/2014
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).