Date de publication: 15 juillet 2015
Promoteur – Intermédiaire Financier
HUNGARYLieu
Description
The project is a major project allocation under the Regional Accessibility Co-Financing framework loan and consists of the rehabilitation of approximately 70 km of Main Road 55 (2x1 lanes) between Baja and Szeged in Hungary and the construction of a 7 km bypass of Mórahalom.
Objectifs
Road 55 is located on the comprehensive TEN-T road network. The road has both local and strategic functions serving towns and villages along the route and wider transit traffic – principally between Hungary, Slovenia, Croatia and Romania. The rehabilitation of Road 55 is expected to provide travel time savings, improve journey time reliability and reduce vehicle operating costs for road users and reinforce its local, regional and strategic role.
Secteur(s)
- Transports - Transports et entreposage
Montant BEI envisagé (montant approximatif)
EUR 49 million
Coût total (montant approximatif)
EUR 124 million
Aspects environnementaux
The project was included in the Transport Operational Programme 2007-2013, National Transport Strategy and the National Spatial Plan. All were subject to strategic environmental assessment according to Directive 2001/42/EC. The project – both the rehabilitation sections and new bypass construction – are classes of development that fall under Annex II of the Environmental Impact Assessment (EIA) Directive 2011/92/EU. The project was screened out of further assessment and a full EIA procedure was not required. A screening on nature conservation areas was also undertaken. The project has received environment decisions by the national competent authorities.
Passation des marchés
The promoter is a public entity obliged to comply with the European and national public procurement legislation. Works, design service and supervision contracts were procured for the four project sections and lots. The contracts were published including in the Official Journal of the European Union (OJEU), in accordance with Directive 2004/18/EC, using open procedure, and were awarded on lowest price.
Statut
Approuvé - 22/09/2015
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).