Date de publication: 15 mai 2018
Promoteur – Intermédiaire Financier
KINGDOM OF LESOTHOLieu
Description
The Lowlands Water Development Project (LWDP) is the second phase of the Lesotho Lowland Water Supply Scheme (LLWSS). It will include bulk water production infrastructure, distribution networks and actions on water efficiency, sanitation and capacity building. The first phase, the Metolong Dam and Water Supply Program (MDWSP), was already financed by the Bank.
Objectifs
The overall LLWSC aims at improving the climate resilience and security of potable water access in four priority geographical zones of the Lowlands of Lesotho.
Secteur(s)
- Eau, assainissement - Production et distribution d'eau; assainissement, gestion des déchets et dépollution
Montant BEI envisagé (montant approximatif)
EUR 116 million
Coût total (montant approximatif)
EUR 200 million
Aspects environnementaux
A Resettlement Policy framework has been developed as well as an Environmental and Social Management Framework. Terms of reference for the Environmental and Social Impact Assessment (ESIA) and Resettlement Action Plan (RAP) are being prepared.
Passation des marchés
EIB will require the promoter to ensure that implementation of the project will be done in accordance with the EIB Guide to Procurement.
Statut
Signé - 1/04/2019
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).