Référence: 20170828
Date de publication: 9 mars 2018

Promoteur – Intermédiaire Financier

PUBLIC ENTITY(IES)

Lieu

Description

Upgrading and widening the M15 expressway to a 2-lane double-carriageway motorway between the M1 Motorway and Rajka at the Hungarian and Slovakian border.

Objectifs

This project will upgrade the 14.5-km long M15 expressway to a 2-lane dual carriageway motorway, with emergency lanes, separation of directions, interchanges and a maximum speed of 130 km/h, matching the standard of the adjacent D2 motorway in Slovakia and the M1 motorway in Hungary.

Secteur(s)

Montant BEI envisagé (montant approximatif)

EUR 17 million

Coût total (montant approximatif)

EUR 73 million

Aspects environnementaux

The Hungarian national law was followed on Environmental Impact Assessment (EIA), which is compliant with the EIA Directive 2011/92/EU, the Habitats Directive 92/43/EEC, and the Birds Directive 2009/147/EC. The construction and operation of the project is expected to impact soils, ground and surface waters, flora and fauna, landscape, built environment, air quality and noise. Natura 2000 special bird reservation area is found all along the track. Measures to reduce impacts are included in the project design and consist of landscaping, water and soil protection, vegetation planting and integration of noise protection measures. Since the scope of works is limited to widening and upgrade, the completed project is expected to have minimal negative effects on the environment and is expected not to breach EU directives on biodiversity.

Passation des marchés

The promoter has tendered works and supervision contracts in accordance with the relevant applicable EU procurement legislation, Directive 2014/24/EU, with the publication of tender notices in the Official Journal of the European Union in 2016. Both Works and Engineering contracts were signed in August and March 2017, respectively.

Statut

Approuvé - 16/03/2018

Clause de non-responsabilité

Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

Mots-clés correspondants

Hongrie Transports