Date de publication: 26 septembre 2018
Promoteur – Intermédiaire Financier
MINISTRY OF PUBLIC WORKS - REPUBLIC OF LIBERIALieu
Description
The EIB loan will fund upgrading and paving of Sanniquellié-Loguatou road, a major link connected with the Trans-West African Highway linking Nouakchott-Dakar-Lagos. In particular, the project concerns the rehabilitation of 47 km of the gravel road and other infrastructures.
Objectifs
The project will contribute to the reduction of poverty by improving transport infrastructures and the conditions alongside the rehabilitated road connecting Liberia to Ivory Coast. The overall objective is to boost the post-conflict economic recovery of the two countries in the Mano River Union (MRU) region by improving intra-community and regional trade. The corridor, with its alignment alternatives, connects all the ports and all the main cities of Liberia and is as such an extremely important nation building/connecting element. Specifically, the project seeks to improve transport conditions in order to reduce costs, facilitate free movements of persons and goods and increasing living conditions of the surrounding communities.
Secteur(s)
- Transports - Transports et entreposage
Montant BEI envisagé (montant approximatif)
EUR 20 million
Coût total (montant approximatif)
EUR 59 million
Aspects environnementaux
The Project is expected to have an impact on the physical, biological and social resources through land take and impact on ecosystem services. The main potential negative impacts relate to: (i) the destruction of the flora and the disturbance of the fauna in the project areas; (ii) water and soil pollution; (iii) destruction / desecration of cultural sites, including sacred forests along roadsides; (iv) complete or partial destruction of property (dwelling houses, commercial facilities, etc.), (v) the spread of HIV / AIDS (to give an indication, the HIV prevalence rate in Nimber county is at 35%); and (vi) increased traffic accidents. These negative impacts should be mitigated through the application of appropriate measures contained in the Environmental and Social Management Plans (ESMP) as well as in the Resettlement Action Plans (RAPs). Also, from the start of the project, the project is expected generate positive impacts through job creation and the development of income-generating activities.
Passation des marchés
Promoter will have to ensure that any procurement procedures will be carried out in accordance with EIB Guide to Procurement.
Statut
Signé - 2/12/2019
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.