Date de publication: 19 novembre 2019
Promoteur – Intermédiaire Financier
METLEN ENERGY & METALS SALieu
Description
The project will finance the construction of a new natural gas-fired combined-cycle gas turbine (CCGT) power plant at Agios Nikolaos, Viotias.
Objectifs
The new CCGT power plant will have a nominal capacity of 826MW.
Secteur(s)
- Énergie - Production et distribution d'électricité, de gaz, de vapeur et d'air conditionné
Montant BEI envisagé (montant approximatif)
EUR 125 million
Coût total (montant approximatif)
EUR 322 million
Aspects environnementaux
An Environmental Impact Assessment (EIA) has been completed for the plant and the Environmental Permits have been approved by the Competent Authorities. The promoter has indicated that no E&S issues or concerns have arisen during public consultation period. Emissions from the plant will be in line with the relevant EU directive requirements.
Passation des marchés
The promoter is an operator in the private sector in the sense of the EIB's Guide to Procurement. The project will be implemented by the promoter's Engineering, Procurement, Construction (EPC) business unit. The main equipment supply has been competitively tendered and has been awarded to a leading equipment supplier.
Statut
Signé - 21/07/2020
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).