Date de publication: 26 mai 2021
Promoteur – Intermédiaire Financier
TENNET HOLDING BVLieu
Description
The project comprises the construction of a c. 41-km long electricity transmission corridor from Eemshaven to Vierverlaten, in the north of the Netherlands. It includes a new 380kV line from Eemshaven to Vierverlaten, combined with a 110kV line for part of the route, and a new 380/220kV substation in Vierverlaten.
Additionality and Impact
The project comprises the construction of a 41km-long electricity transmission corridor from Vierverlaten to Eemshaven, in the Netherlands. It will increase the capacity of the Dutch electricity transmission system, ensure compliance with the Dutch Grid Code for this part of the network and support the integration of cross-border connection into the Dutch grid. It is fully consistent
with and supports national and EU policies on energy and climate. It helps
addressing the market failure caused by negative environmental externalities, by enabling the future integration of renewable generation, while also contributing to
the provision of a public good (security and reliability of supply), by enhancing a critical infrastructure for
decarbonisation.
The project's results are deemed good in
terms of economic welfare by virtue of the benefits it generates, as well as
from the environmental, social, and governance viewpoints.
The financing of the EIB is
functional to enabling the ambitious CAPEX plan that the Promoter foresees as
fundamental for the transition to a decarbonised economy. The EIB contribution
materialises in terms of diversification of sources of funds, attractive
financing conditions, and signalling to markets.
Objectifs
The overall purpose of the project is to increase the Netherland's electricity transmission capacity and to enable the evacuation of power from offshore wind farms.
Secteur(s)
- Énergie - Production et distribution d'électricité, de gaz, de vapeur et d'air conditionné
Montant BEI envisagé (montant approximatif)
EUR 250 million
Coût total (montant approximatif)
EUR 527 million
Aspects environnementaux
The potential environmental impacts of the project include visual impact, vegetation clearance, electromagnetic fields, noise nuisance, and birds' collision and electrocution. The project falls under Annex I of the EIA directive, thus requiring an environmental impact assessment (EIA). The Environmental Impact Studies (EISs) have been prepared and the relevant approvals have been issued by the competent authorities. The EIS(s) and the planned mitigation measures will be reviewed during appraisal.
Passation des marchés
The Bank will require the Promoter to ensure that contracts for the implementation of the project have been and will be tendered in accordance with the relevant applicable EU procurement legislation (Directive 2014/25/EU where applicable), as interpreted by the Court of Justice of the EU, with publication of tender notices in the Official Journal of the EU, as and where required.
Statut
Signé - 16/09/2021
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).