Date de publication: 28 octobre 2022
Promoteur – Intermédiaire Financier
SPECIAL PURPOSE ENTITY(IES)/FUNDLieu
Description
The project includes the design, implementation and operation of 2 (two) very large-scale, fixed-bottom offshore windfarms (Baltica 2, Baltica 3) with a total capacity of up to 2.5 GW. Baltica 2 (1.5 GW) and Baltica 3 (1 GW) are both located in the Baltic Sea, inside the the Polish Economic Exclusive Zone.
Objectifs
The offshore wind farms will primarily reduce carbon and air pollution emissions, which are externalities the market fails to address. Moreover, the project should foster the integration of new, variable renewable generation technologies in the market. The proposed EIB loan would thus fill a market gap in the development of new renewable capacity. That would include a financing gap for projects that try to develop new capacity with more market-exposed structures and instruments.
Secteur(s)
- Énergie - Production et distribution d'électricité, de gaz, de vapeur et d'air conditionné
Montant BEI envisagé (montant approximatif)
EUR 1400 million
Coût total (montant approximatif)
EUR 9845 million
Aspects environnementaux
Wind farms adhere to the national legislation having transposed Annex II of Directive 2014/52/EU amending Directive 2011/92/EU, thereby leaving it to the competent authority to determine if an Environmental Impact Assessment (EIA) is mandated. Given the project size, the competent authority required an EIA to be conducted. Compliance of the authorisation process with relevant EU Directives will be verified during appraisal.
Passation des marchés
It is provisionally understood that the promoter, which are a Special Purpose Vehicles (SPV), are neither - in the sense of the EU procurement policies - a contracting authority nor a public undertaking. It also does not see to operate on the basis of special or exclusive rights granted by a competent authority in relation to this project. Consequently, no public procurement would be required. However and as indicated by the promoter, the SPVs, when tendering and awarding contracts, take the rules of the EU procurement directives as guiding principles. The impact of this approach to the project needs to be assessed during appraisal.
Statut
Approuvé - 12/07/2023
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).