Construction of a 50 MW geothermal power plant as a privately developed Independent Power Producer (IPP) in Tulu Moye, Oromia State, Ethiopia, that will provide a capacity increase and diversification of energy resources in Ethiopia.
Investment in geothermal energy will help reduce power outages and meet the rapid growth in demand, and with lower greenhouse gas (GHG) emissions than fossil-fuel-based alternatives, thereby supporting the sustainable economic development of Ethiopia. The project contributes to EU renewable energy and environmental policies (particularly climate change policies) and several Sustainable Development Goals (SDGs), especially SDG 7 - access to affordable and clean energy.
If located in the EU, the project would fall under Annex II of the EU EIA Directive, requiring a screening decision by the competent authority. In accordance with the Ethiopian Environmental Impact Assessment Proclamation 299/2002, an Environmental and Social Impact Assessment (ESIA) has been carried out, covering the impacts of constructing a 100 MW power plant with associated drilling, steamfield collection and grid connection. The ESIA, which also includes the results from the public consultation and participation, was approved by the Ministry of Water Irrigation and Energy in June 2018 and received clearance in accordance with the Federal Environmental Protection Authority. The key potential adverse impacts identified are involuntary resettlement owing to land use change, noise, air quality, archaeology and cultural heritage sites, landscape and wildlife. The Bank will assess environmental and social aspects during appraisal to check alignment with EIB Environmental and Social Standards. In particular, the Bank will review that appropriate public consultations have been carried out during the ESIA process as well as request a Stakeholder Engagement Plan at the level of the project, inclusive of a Grievance Mechanism. Environmental and social impacts of the project, inclusive of the transmission line, will be appraised in accordance with the Bank's environmental and social standards.
The exploration license has been, and the geothermal well-field development and use license is expected to be, awarded to the Promoter on an exclusive basis. In the absence of competition related to the award of the exploration and operating licenses, the PPA will be reviewed to assess whether it is economically reasonable in terms of price, quality and risk-sharing and the works, goods and services covered by the Bank's financing will be considered as operations in the public sector from a procurement perspective as defined in the EIB Guide to Procurement. The Bank will ensure that implementation of the project will be done in accordance with the Bank's Guide to Procurement.
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).
Dokumente
Allgemeine Fragen und Anmerkungen
Die EIB betreibt eine offene Kommunikation und ermutigt Interessenträgerinnen und Interessenträger, sich konstruktiv einzubringen.
Anmerkungen und Fragen zur Beteiligung der EIB an einem Projekt oder zu Finanzierungen, zur Arbeit, zur Organisation oder zu den Zielen der EIB können an den EIB Infodesk gerichtet werden.
Alternativ können Sie über die Außenbüros der EIB Kontakt mit der Bank aufnehmen.
Fragen zu Einzelheiten eines konkreten Projekts sollten möglichst direkt an den Projektträger gerichtet werden, besonders, wenn sich das Vorhaben bei der EIB noch im Prüfungsstadium befindet.
Medienanfragen
Medienanfragen können Sie an die Pressestelle der EIB richten. Bitte besuchen Sie auch unseren Pressebereich.
Beschwerdemechanismus
Für Beschwerden über mutmaßliche Missstände in der Tätigkeit der Bank steht der Beschwerdemechanismus der EIB zur Verfügung. Der Europäische Bürgerbeauftragte untersucht als unabhängige Stelle Beschwerden und verlangt Rechenschaft von der EIB.
„Null Toleranz“ gegenüber Betrug und Korruption
Die Bank duldet unter keinen Umständen Betrug oder Korruption. Bitte richten Sie Betrugs- oder Korruptionsbeschwerden direkt an die Abteilung Betrugsbekämpfung. Alle Beschwerden werden streng vertraulich und in Übereinstimmung mit den Untersuchungsverfahren der EIB und den Leitlinien für Betrugsbekämpfung behandelt.
Weitere Veröffentlichungen