Veröffentlichungsdatum: 13 Juni 2003
Projektträger – zwischengeschaltetes Finanzinstitut
Aer Rianta cpt
Contact: Marion O'Brien, Group Head of Corporate Finance
Ort
Beschreibung
Construction of a new passenger terminal at Cork airport including hold baggage screening facility, landside development of access egress/roads, infrastructure services and car parking.
Ziele
The existing Cork terminal has a design capacity of 1.1 million passengers per annum and was used by up to 1.9 million passengers in 2002. The project will provide capacity for 3 million passengers per annum, thus alleviating congestion on the terminal system and improving access and parking facilities.
Kommentar(e)
Airports
Sektor(en)
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
Loan circa EUR 110 million
Gesamtkosten (voraussichtlicher Betrag)
Estimated at circa EUR 150 million
Umweltaspekte
The project is classified under Annex II of EUDirective 85/337 as amended by EU Directive 97/11 EC and has been subject to an Environmental Impact Study. In accordance with its normal procedure, the Bank will ensure that appropriate measures have been defined as regards environmental protection.
Auftragsvergabe
The promoter systematically adopts international competitive bidding procedures in line with EU directives on procurement
Projektstatus
Unterzeichnet - 14/11/2003
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).