Veröffentlichungsdatum: 7 Juli 2009
Projektträger – zwischengeschaltetes Finanzinstitut
ESB – Electricity Supply Board
Ort
Beschreibung
The project concerns the ESB’s wind investment programme for the period 2009 to 2012. The overall capacity will be 214MW. All development will be on-shore operations.
Ziele
The development of wind energy capacity will contribute to environmental and security of energy supply objectives. Electricity generation from onshore wind farms can produce electricity with substantially lower environmental impacts, particularly GHG emissions.
Sektor(en)
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
EUR 175 million.
Gesamtkosten (voraussichtlicher Betrag)
EUR 362 million.
Umweltaspekte
Wind farms fall under Annex II of Directive 85/337/EEC, as amended by Directives 97/11/EC and 2003/35/EC. Thus, the project would be subject to an EIA based on a case-by-case decision or defined criteria set by the competent authorities. The five most advanced projects have all undergone EIA process and have obtained relevant approvals.
Auftragsvergabe
The promoter is a public undertaking according to the EU Procurement Directive and is following public procurement rules for the purchase of the project works including publication of tenders in the Official Journal of the European Union.
Projektstatus
Unterzeichnet - 28/09/2009
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).