Veröffentlichungsdatum: 18 Juni 2009
Projektträger – zwischengeschaltetes Finanzinstitut
A group of private enterprises in the energy sector.
Ort
Beschreibung
The promoter group is developing the Trym gas field under the Norwegian Production License area 147 and linking it to Danish processing and exportation infrastructure. Production is expected to start-up in 2011, with detailed engineering and procurement activities to begin in mid 2009.
Ziele
The intention is to deliver the gas production to European markets, where it will make a contribution to closing the gap between growing demands and declining indigenous supplies. The project is in line with European policy objectives and the Bank’s lending priority regarding security and diversification of energy supply to Member States.
Sektor(en)
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
EUR 90 million.
Gesamtkosten (voraussichtlicher Betrag)
EUR 326 million.
Umweltaspekte
EU environmental regulation requires for projects like the Trym gas field development an environmental impact assessment according to Annex I of the EIA directive. An EIA has been compiled and the approval process from the Norwegian and Danish is currently ongoing.
Auftragsvergabe
The project falls under the public procurement provisions specified by European legislation, here Directive 2004/17/EC. The promoter informed that tendering follows such provisions.
Projektstatus
Unterzeichnet - 6/10/2010
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).