Suche starten De menü de ClientConnect
Suche starten
Ergebnisse
Top-5-Suchergebnisse Alle Ergebnisse anzeigen Erweiterte Suche
Häufigste Suchbegriffe
Meistbesuchte Seiten
    Referenz: 20090674
    Veröffentlichungsdatum: 16 April 2010

    Projektträger – zwischengeschaltetes Finanzinstitut

    Kenya Electricity Generating Company Ltd. (KenGen)

    Ort

    Beschreibung

    Expansion of existing Olkaria I and new Olkaria IV Geothermal power station to increase generation capacity by a further 280 MW (2x70 MW at each of Olkaria I and IV).

    Ziele

    The project will help meet growing electricity demand at a competitive cost and with a limited impact on the environment. Its economic benefits include increased power production, improved security of supply (geothermal power is unaffected by annual hydrological conditions), reduced national dependence on imported fossil fuels for electricity production and additional operational flexibility for existing units at two geothermal power plants.

    Sektor(en)

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    EUR 120 million.

    Gesamtkosten (voraussichtlicher Betrag)

    EUR 1 007 million.

    Umweltaspekte

    An environmental and social impact assessment (ESIA) has been established for both power stations. The studies comprise public consultation and respective monitoring plans. The studies have been approved and respective licenses issued by NEMA (National Environmental Management Authority).

    The Olkaria IV part requires resettlement of several Maasai communities. A Resettlement Action Plan (RAP) has been established, which included the participation of the project affected communities. The execution of the RAP will be implemented according to the WB guidelines.

    Auftragsvergabe

    Kenyan national law, IDA guidelines (which govern the whole Electricity Expansion Project), EU Directives (2004/17 replacing 93/38) and EIB procurement guidelines require an open tendering procedure with adequate publication for works contracts of this type launched by a public sector company. The promoter will follow these rules and envisages among others a publication of the prequalification notice in the OJEU for the main contracts.

    These procurement procedures are in line with the Bank’s procurement guidelines, are considered adequate for the project and satisfactory to the Bank.

    Projektstatus

    Unterzeichnet - 15/12/2010

    Haftungsausschluss

    Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
    Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

    Tags

    Kenia Energie