Suche starten De menü de ClientConnect
Suche starten
Ergebnisse
Top-5-Suchergebnisse Alle Ergebnisse anzeigen Erweiterte Suche
Häufigste Suchbegriffe
Meistbesuchte Seiten
    Referenz: 20090728
    Veröffentlichungsdatum: 30 April 2010

    Projektträger – zwischengeschaltetes Finanzinstitut

    Tanzania Electric Supply Company (TANESCO)

    Ort

    Beschreibung

    The project involves the construction of a 667 km transmission line, operated at 220kV with both circuit strung, between Iringa and Shinyanga.

    Ziele

    The project will link existing and future generating sources in the south and southwest of Tanzania to the load centers in the Mwanza and Arusha regions, in the north. The north-west part of Tanzania is experiencing a fast increase in electricity demand of around 10% annually due to the growth of mining activities. The existing transmission line has reached its technical limit to carry additional power and the planned connections of rural, urban and industrial customers will increase the network overload. The project might also anticipate future interconnections with Kenya in the north and Zambia in the south.

    Sektor(en)

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    EUR 130 million.

    Gesamtkosten (voraussichtlicher Betrag)

    EUR 400 million.

    Umweltaspekte

    Due to the project’s caracteristics, the Tanzanian legislation requires an environmental and social impact assessment including an environmental and social mitigation plan and a social and environmental monitoring plan. In addition, a resettlement action plan has been elaborated. The ESIA prepared by an independent consultant has been submitted to the approval of the Tanzanian authorities.

    Auftragsvergabe

    The procurement of the section to be financed by the Bank will be carried-out in line with the requirements of the Bank’s Guidelines to Procurement. Other contracts will also be tendered internationally, in line with the rules of the other lenders involved.

    Projektstatus

    Unterzeichnet - 14/12/2010

    Haftungsausschluss

    Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
    Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

    Tags

    Tansania Energie