Suche starten De menü de ClientConnect
Suche starten
Ergebnisse
Top-5-Suchergebnisse Alle Ergebnisse anzeigen Erweiterte Suche
Häufigste Suchbegriffe
Meistbesuchte Seiten
Referenz: 20100149
Veröffentlichungsdatum: 29 April 2010

Projektträger – zwischengeschaltetes Finanzinstitut

Stadtwerke München GmbH

Ort

Beschreibung

The project comprises a large number (several hundreds) of independent schemes for reinforcing and modernising the electricity distribution grid system of Munich over the 3-year investment period. The investments include refurbished, enlarged and new assets at voltage levels of 110 kV to 0.4 kV, including 110 kV cables and transformers, 10 kV cables, 0.4 kV cables, connections and substations, as well as metering and control systems.

Ziele

The investment programme aims at grid optimisation and sustaining network efficiency, reliability and safety. It also includes replacement of obsolete material and improvement of environmental impact. Several investments serve to cater for the connection of new system users, both on the supply side (growing decentralised energy efficient and renewable power production) and the demand side (residential, commercial and industrial sector developments).

Sektor(en)

Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

EUR 100 million.

Gesamtkosten (voraussichtlicher Betrag)

EUR 200 million.

Umweltaspekte

The promoter has informed the Bank that none of the schemes pertain to Annex I of Directive 97/11/EC, and that equally the authorities have not required an EIA for any of the schemes. He has also informed the Bank that none of the schemes impact on a Natura 2000 area. The grid company is undergoing every two years an eco-management and audit scheme and is EMAS certified. The schemes are located within urban areas and in new commercial and industrial centres with no particular environmental issues involved.

Auftragsvergabe

The promoter confirmed adhering to EU legislation in its procurement procedures for the investment programme’s services, supply and work contracts. The promoter applies mainly restricted procedures with a system for qualification of suppliers. As and where required, tender notices and systems for qualification will be published in the OJEU.

Projektstatus

Unterzeichnet - 22/07/2011

Haftungsausschluss

Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

Tags

Deutschland Energie