Veröffentlichungsdatum: 15 September 2011
Projektträger – zwischengeschaltetes Finanzinstitut
STATNETT SF
Ort
Beschreibung
Implementation of a monopolar High Voltage Direct Current link interconnecting Norway and Denmark across the Skagerrak strait including two terminal converter stations located in Kristiansand (Norway) and Tjele (Denmark), 140 km of undersea cable and 102 km of land cable.
Ziele
The purpose is to increase the transmission capacity between Denmark and Norway to allow more electricity trade between the Norwegian and the European continental markets – essentially the markets in Denmark and Germany.
Sektor(en)
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
Up to EUR 200 million
Gesamtkosten (voraussichtlicher Betrag)
Up to EUR 400 million
Umweltaspekte
The project received all the necessary environmental approvals by the competent authorities in both Norway and Denmark. No significant long-term impacts are expected to result from project construction and operation.
Auftragsvergabe
In line with the requirements of the EU Directive 2004/17/EC, the procurement of the project has followed negotiated procedures with prior publication of calls for qualification in the OJEU.
Projektstatus
Unterzeichnet - 21/12/2011
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).