Suche starten De menü de ClientConnect
Suche starten
Ergebnisse
Top-5-Suchergebnisse Alle Ergebnisse anzeigen Erweiterte Suche
Häufigste Suchbegriffe
Meistbesuchte Seiten
Referenz: 20130468
Veröffentlichungsdatum: 18 Juni 2014

Projektträger – zwischengeschaltetes Finanzinstitut

MOROCCAN AGENCY FOR SOLAR ENERGY

Ort

Beschreibung

Construction and operation of a 150 MW concentrating solar power (CSP) Tower plant under the third phase of the Ouarzazate solar power complex.

Ziele

The project's main objective is to help developing a globally-available, non-carbon power generation technology that ultimately may not require fossil fuel back-up capacity and reduce the costs of CSP for world benefit. By creating a new green industry and increasing the penetration of renewable energy in the country's energy mix, the project will contribute to Morocco's objectives of a more secure energy supply, energy diversification, CO2 emission reductions, increased employment, and protecting the local environment.

Kommentar(e)

This operation is covered by the EU Guarantee for EIB loans outside the EU.

Sektor(en)

Garantie im Rahmen des Außenmandats

This operation is covered by the ELM Guarantee.

Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

EUR 82 million

Gesamtkosten (voraussichtlicher Betrag)

EUR 855 million

Umweltaspekte

If the project were located in the EU, it would fall under Annex II of the Environmental Impact Assessment (EIA) Directive (85/337/EEC) as amended, requiring the competent national authority to determine the need for an EIA. Under Moroccan Law, the project requires a mandatory EIA including initial scoping and public consultation. During appraisal, the Bank will ensure that the project complies with the Bank's principles and standards as regards environmental and social issues.

Auftragsvergabe

Within the EU, the promoter, being a public contracting authority, would be subject to public procurement procedures according to 2004/17/EU, including publication of contract notices in the Official Journal of the EU. In line with the Bank's principles and its statute, the promoter is following the provisions of the Bank's Guide to Procurement, which includes amongst others international competitive bidding and Official Journal of the EU contract notice publication for the items to be financed by the Bank.

Projektstatus

Unterzeichnet - 22/12/2014

Haftungsausschluss

Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

Tags

Marokko Energie