Suche starten De menü de ClientConnect
Suche starten
Ergebnisse
Top-5-Suchergebnisse Alle Ergebnisse anzeigen Erweiterte Suche
Häufigste Suchbegriffe
Meistbesuchte Seiten
Referenz: 20150008
Veröffentlichungsdatum: 18 September 2017

Projektträger – zwischengeschaltetes Finanzinstitut

SOCIETE NATIONALE INDUSTRIELLE ET MINIERE

Ort

Beschreibung

The project consists of the dredging works related to the deepening and enlargement of the access channel to the Port of Nouadhibou solid bulk terminal, where iron ore from the Société Nationale Industrielle et Minière (SNIM) production facilities is handled. The project will allow bigger vessels to berth at the SNIM terminal increasing the environmental sustainability of the supply chain associated to SNIM's business model.

Ziele

The project consists of the capital dredging works related to the deepening and enlargement of the access channel to the Port of Nouadhibou solid bulk terminal, where iron ore from the SNIM production facilities is handled. The project will allow bigger vessels to berth at the SNIM terminal increasing the operational efficiency and environmental sustainability of the supply chain associated to the business model of SNIM. The construction is expected to last a total of 14 months.

Kommentar(e)

The Borrower is a repeat and long-term client of the EIB.

Sektor(en)

Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

EUR 50 million

Gesamtkosten (voraussichtlicher Betrag)

EUR 119 million

Umweltaspekte

If within the EU, the project would fall under Annex I of the EIA Directive 2011/92/EU and would require a full Environmental Impact Assessment (EIA). In compliance with these requirements, an environmental and social impact assessment (ESIA) is being prepared and public consultations shall be undertaken. Once the ESIA is approved by the environmental authority, an enhanced Environmental and Social Management Plan (ESMP) will also be prepared. During the appraisal process the Bank will check the compliance of the above mentioned procedures and documents with the EIB's environmental and social standards.

Auftragsvergabe

The Bank will require the promoter to ensure that all contracts for the implementation and operation of the project have been or shall be tendered in accordance with the Bank's Guide to Procurement. Procurement procedures and status for the various project components will be checked in detail during the appraisal process.

Projektstatus

Unterzeichnet - 28/06/2018

Haftungsausschluss

Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

Tags

Mauretanien Verkehr