Veröffentlichungsdatum: 22 Juni 2016
Projektträger – zwischengeschaltetes Finanzinstitut
LAND BADEN-WUERTTEMBERGOrt
Beschreibung
Investment in rolling stock in Baden-Württemberg (Network 9b Freiburger Y). Sub-operation under programme loan for rolling stock and related infrastructure for local and regional public transport in Baden-Württemberg.
Ziele
The new rolling stock will improve public transport services in the Freiburg region. More passengers should be attracted to public transport, resulting in improvements in overall mobility while reducing the adverse impact of transport on the environment.
Sektor(en)
- Verkehr - Verkehr und Lagerei
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
EUR 25 million
Gesamtkosten (voraussichtlicher Betrag)
EUR 52 million
Umweltaspekte
The manufacture of rolling stock does not fall under either Annex I or Annex II of the Environmental Impact Assessment (EIA) Directive 2011/92/EU as amended. It is not clear yet if any depots are necessary at this stage. As an associated facility, a new depot might be necessary. This could fall under Annex II of the EIA Directive, and therefore may be subject to an EIA procedure. German law requires compliance with Directive 2011/92/EU, as amended, to obtain building permits for such elements. If construction of a new facility is required, the promoter undertakes to inform the Bank on environmental compliance by submitting a copy of the environmental decision and the non-technical summary of the EIA (if applicable), as well as evidence that the requirements of the Habitats Directive 92/43/EEC and the Birds Directive 79/409/EEC have been fulfilled if applicable.
Auftragsvergabe
The Bank will require the promoter to ensure that contracts for the implementation of the project have been and shall be tendered in accordance with the relevant applicable EU procurement legislation (Directives 2004/18/EC and/or 2004/17/EC as well as Directives 89/665/EEC and 92/13/EEC) as interpreted by the Court of Justice of the EU, with publication of tender notices in the Official Journal of the EU, as and where required. Network 9b is published under 2015/S 250-458133, d.d . 26-12-2015.
Projektstatus
Unterzeichnet - 3/05/2017
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).