The Slovenian Celje-Pragersko railway line is located on the Baltic-Adriatic and Mediterranean Core Network Corridors. The line currently represents a bottleneck in passenger and freight transport due to insufficient load capacity and limited interoperability. The project concerns construction works in the Poljcane station, the Poljcane–Slovenska Bistrica section and the Slovenska Bistrica station. The works cover reconstruction of substructure and superstructure, construction of platforms, grade-separated crossings, underpasses, as well as adjustments of energy, signalling-safety and telecommunication devices.

Ziele

The project will upgrade the Poljcane-Slovenska Bistrica double-track section with the main objective of increasing the load capacity and improving the interoperability of the railway line.

Sektor(en)

Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

EUR 18 million

Gesamtkosten (voraussichtlicher Betrag)

EUR 58 million

Umweltaspekte

The pertinence to Annexes I and II of the Environmental Impact Assessment (EIA) Directive, the screening decisions, the EIA and the development consents will be reviewed during appraisal. The project's potential impact on protected areas and species, in accordance with the Habitats Directive (92/43/EEC) and Birds Directive (2009/147/EC) will also be appraised. A modal shift thanks to increased rail-based mobility can be expected (due to increased speed and capacity), thus also decreasing traffic-related greenhouse gas emissions, although to a limited extent. Details will be checked during appraisal.

Auftragsvergabe

The Bank will require the promoter to ensure that contracts for the implementation of the project have been/shall be tendered in accordance with the relevant applicable EU procurement legislation (Directive 2004/17/EC, or 2014/25/EU where applicable, as well as Directives 89/665/EEC and 92/13/EEC), as interpreted by the Court of Justice of the EU, with publication of tender notices in the Official Journal of the EU, as and where required.

Projektstatus

Genehmigt - 27/10/2017

Haftungsausschluss

Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

Tags

Slowenien Verkehr