Veröffentlichungsdatum: 28 September 2017
Projektträger – zwischengeschaltetes Finanzinstitut
ELECTRICITY SUPPLY BOARD, BORD NA MONAOrt
Beschreibung
Construction and operation of an onshore wind farm consisting of up to 30 wind turbines with a total capacity of 89MW in County Mayo, Ireland
Ziele
The project will contribute to meeting the EU and Irish targets for energy generated from renewable energy sources.
Sektor(en)
- Energie - Energieversorgung
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
EUR 79 million
Gesamtkosten (voraussichtlicher Betrag)
EUR 196 million
Umweltaspekte
The project is fully consented following an environmental impact assessment process. The project has no significant negative impact on the integrity of any nature conservation site.
Auftragsvergabe
The Bank will require the promoter to ensure that contracts for the implementation of the project have been/shall be tendered in accordance with the relevant applicable EU procurement legislation (Directive 2014/25/EU), with publication of tender notices in the Official Journal of the EU, as and where appropriate.
Projektstatus
Unterzeichnet - 22/05/2018
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).