Referenz: 20170923
Veröffentlichungsdatum: 2 Februar 2018

Projektträger – zwischengeschaltetes Finanzinstitut

REPUBLIC OF CROATIA

Ort

Beschreibung

The project aims at reaching compliance with Urban Wastewater Directive for 6 agglomerations on the Island of Krk. The project is co-financed by ESIF (European Structural and Investment Funds) under the Operational Programme Competitiveness and Cohesion and has been reviewed by JASPERS Independent Quality Review (IQR).

Ziele

The project will contribute to Environmental Protection and Natural Resource Efficiency.

Sektor(en)

  • Wasser, Abwasser - Wasserversorgung; Abwasser- und Abfallentsorgung und Beseitigung von Umweltverschmutzungen

Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

EUR 6 million

Gesamtkosten (voraussichtlicher Betrag)

EUR 69 million

Umweltaspekte

The project's components will contribute to ensure compliance with key EU directives in the water sector notably the Urban Waste Water Treatment Directive (91/271/EC) and the Water Framework Directive (2000/60/EC). Where and if applicable, the requirements of the EIA Directive 2011/92/EU as amended by 2014/52/EU and SEA Directive 2001/42/EC will be respected. The promoter will in such case, prior to utilizing any EIB funds, be responsible for transmitting to the Bank the non-technical summary of the Environmental Impact Assessment (EIA). For any part of the project that may impact on a nature conservation site, the promoter will be required to provide to the Bank an approval of the competent authority and information on the mitigating measures required to comply with the Habitats Directive 92/43/EEC.

Auftragsvergabe

The Bank will require the promoter to ensure that contracts for the implementation of the project will be tendered in accordance with the relevant applicable EU procurement legislation (Directives 2014/23/EU, 2014/24/EU or 2014/25/EU, where applicable, as well as Directives 92/13/EEC and 89/665/EEC) as interpreted by the Court of Justice of the European Union, with publication of tender notices in the Official Journal of the European Union (OJEU), as and where required.

Projektstatus

Genehmigt - 9/04/2018

Haftungsausschluss

Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

Tags

Kroatien Wasser, Abwasser