Veröffentlichungsdatum: 3 Oktober 2019
Projektträger – zwischengeschaltetes Finanzinstitut
ENERGIE STEIERMARK AG,ENERGIENETZE STEIERMARK GMBHOrt
Beschreibung
The project is an investment programme that comprises number of schemes in the electricity and gas distribution network of the Austrian Federal State of Styria. The project includes the rollout of smart meters and ICT activities to facilitate the transition to a smart distribution network.
Ziele
The programme will allow the promoter to maintain or improve the reliability and quality standards of electricity supply, connect new users including renewable generators and the roll-out of smart meters.
Sektor(en)
- Energie - Energieversorgung
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
EUR 180 million
Gesamtkosten (voraussichtlicher Betrag)
EUR 385 million
Umweltaspekte
The programme schemes are expected to have limited environmental consequences. Environmental impact studies will be carried out as applicable and mitigating and/or compensation measures will be applied as necessary.
Auftragsvergabe
The EIB will require each promoter to ensure that contracts for the implementation of the project have been and will be tendered in accordance with the relevant applicable EU procurement legislation (Directive 2014/25/EU where applicable, as well as Directive 92/13/EEC or Directive 89/665/EEC), as interpreted by the Court of Justice of the EU, with the publication of tender notices in the Official Journal of the EU, as and where required.
Projektstatus
Unterzeichnet - 30/09/2019
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).