Referenz: 20190378
Veröffentlichungsdatum: 26 März 2020

Projektträger – zwischengeschaltetes Finanzinstitut

LG CHEM WROCLAW ENERGY SP ZOO

Ort

Beschreibung

The project will finance the design, construction, commissioning and operation of an innovative large-scale integrated lithium-ion battery cells-to-packs manufacturing facility for the supply of European automotive manufacturers with advanced 3rd generation li-ion batteries for electric vehicles.

Ziele

The objective is to offer Europe the prospect of a cost-competitive Li-ion battery cells supply basis, enhancing independence from imports. The project will seek to be competitive through a vertical integrated production process, high degree of automatisation and digitalisation, and a maximum of components and materials sourced in Europe.

Sektor(en)

  • Industrie - Verarbeitendes Gewerbe/Herstellung von Waren

Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

EUR 480 million

Gesamtkosten (voraussichtlicher Betrag)

EUR 1514 million

Umweltaspekte

The project concerns capital investments for the production of lithium-ion electrodes, cells and batteries, falling under the Environmental Impact Assessment (EIA) Directive 2014/52/EU amending the EIA Directive 2011/92/EU. All environmental, health and safety issues including environmental and operational authorisations will be reviewed during the due diligence process.

Auftragsvergabe

The promoter has been assessed by the EIB as being a private company not being subject to EU rules on public procurement or concessions. However, if after the project appraisal, the EIB were to conclude that the promoter is after all subject to EU public procurement legislation Directive 2014/25/EU then the Bank would require the promoter to ensure that contracts for the implementation of the project will be tendered in accordance with the relevant applicable EU procurement legislation 2014/25/EU, as well as Directive 92/13/EEC as interpreted by the Court of Justice of the EU, with publication of tender notices in the EU Official Journal, as and where required.

Projektstatus

Unterzeichnet - 6/03/2020

Haftungsausschluss

Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

Tags

Polen Industrie