Veröffentlichungsdatum: 24 Juni 2020
Projektträger – zwischengeschaltetes Finanzinstitut
COPENHAGEN INFRASTRUCTURE PARTNERS P/SOrt
Beschreibung
The project will finance the implementation of a portfolio of onshore wind farms located in the Spanish region of Aragon, for a total capacity of 487MW.
Ziele
The project refers to a project finance operation for the implementation of a portfolio of onshore wind farms, for a total capacity of ~487 MW, located in the Spanish region of Aragon.
Sektor(en)
- Energie - Energieversorgung
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
EUR 90 million
Gesamtkosten (voraussichtlicher Betrag)
EUR 468 million
Umweltaspekte
With regard to the environmental and social aspects, the plants fall in Annex II of the Directive 2014/52/EU amending the Environmental Impact Assessment (EIA) Directive 2011/92/EU, and because of their technical features, have been screened in by the competent authority. The promoter performed EIA processes for the plants and interconnection infrastructure. All facilities possess environmental licenses. The authorization procedure and compliance with the relevant directives will be further appraised in detail; this concerns in particular the potential need for a cumulative impacts assessment and the impacts on protected flora and fauna, including Natura 2000 sites. No additional details, including detailed location of individual plants, are know at this stage. Finally, in case the promoter intends to use expropriation for certain pieces of land, the process will be assessed at appraisal.
Auftragsvergabe
The promoter has been assessed by the EIB as being a private company not being subject to EU rules on public procurement or concessions . However, if after the project appraisal, the EIB were to conclude that the promoter is after all subject to EU public procurement legislation: Directive 2014/23/EU / 2014/24/EU or 2004/18/EC / 2014/25/EU or 2004/17/EC, where applicable, then the Bank would require the promoter to ensure that contracts for the implementation of the will be tendered in accordance with the relevant applicable EU procurement legislation: Directive 2014/23/EU / 2014/24/EU or 2004/18/EC / 2014/25/EU or 2004/17/EC, where applicable, as well as Directive 92/13/EEC or Directive 89/665/EEC] as interpreted by the Court of Justice of the EU, with publication of tender notices in the EU Official Journal, as and where required.
Projektstatus
Unterzeichnet - 16/06/2020
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).