Veröffentlichungsdatum: 29 Juni 2022
Projektträger – zwischengeschaltetes Finanzinstitut
OESTERREICHISCHE BUNDESFORSTE AGOrt
Beschreibung
Construction and operation of four wind turbines with a total capacity of 16.78 MW in the state of Styria, Austria. The project is an extension to an existing wind farm (Pretul).
Ziele
The project contributes to the national renewable energy targets as set out in the final National Climate and Energy Plan, published in December 2019. Austria aims to provide 100% of electricity consumption from renewable energy sources by 2030. The financing of this project also contributes to Bank's lending priority objectives on energy (Renewable Energy) as well as on climate action (transversal).
Sektor(en)
- Energie - Energieversorgung
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
EUR 3 million
Gesamtkosten (voraussichtlicher Betrag)
EUR 21 million
Umweltaspekte
The environmental and social risks associated with such exposed locations can be higher than for other onshore wind farms.
Auftragsvergabe
The EC has exempted all contracts, which are being awarded to implement electricity generation projects in Austria from the scope of the Utilities Directive 2004/17/EC (EC decision 2008/585/EG). No public procurement is therefore required.
Projektstatus
Unterzeichnet - 12/07/2022
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).