The project will finance the construction of a greenfield copper electrolysis plant for high purity cathode fabrication to be installed in Cordoba.
Ziele
The aim is of the new electrolysis plant is to allow the company to internally produce 100,000 tonnes of high purity copper cathodes from 100% copper scrap (recycled copper) in Cordoba. The benefits of the project include lower carbon footprint, improved energy efficiency and improved resilience.
Sektor(en)
- Industrie - Verarbeitendes Gewerbe/Herstellung von Waren
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
EUR 30 million
Gesamtkosten (voraussichtlicher Betrag)
EUR 104 million
Umweltaspekte
The project falls under Annex II of the Environmental Impact Assessment (EIA) Directive 2011/92/EU (as amended by Directive 2014/52/EU), and will require an Environmental Impact Assessment. The project will allows the percentage of scrap material to be increased in copper wire reducing the carbon footprint. The environmental aspects will be further appraised during due diligence.
Auftragsvergabe
The promoter has been assessed by the EIB as being a private company not being subject to EU rules on public procurement or concessions. However, if at the project appraisal, the EIB were to conclude that the promoter is subject to the EU public procurement legislation, then the promoter will have to apply those rules.
Projektstatus
In Prüfung
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).