Veröffentlichungsdatum: 5 August 2024
Projektträger – zwischengeschaltetes Finanzinstitut
VILLE DE PARISOrt
Beschreibung
The project concerns an investment programme for the further development and decarbonisation of the Paris district heating network under its upcoming new concession agreement.
Ziele
The aim is to increase overall energy efficiency of the heating system by expanding the service to new areas, densifying the grid through new connections and upgrading it with new equipment and control systems, in line with the EU and national renewable energy targets. The project is also expected to substitute individual and central fossil fuels heating with more sustainable and efficient centralised heating systems, resulting in primary energy savings and reduction of emissions of greenhouse gases. The detailed project scope is not known at this stage.
Sektor(en)
- Energie - Energieversorgung
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
EUR 375 million
Gesamtkosten (voraussichtlicher Betrag)
EUR 500 million
Umweltaspekte
Based on the technical characteristics and information provided at this stage, the project components would fall under Annex II of the Environmental Impact Assessment Directive (EIA), 2014/52/EU amending 2011/92/EU, which requires the competent national authority to determine the need for an EIA. Potential impacts such as air emissions, groundwater, surface water and soil contamination, impacts on Natura 2000 sites, or noise levels will be reviewed at appraisal.
Auftragsvergabe
Should the concessionnaire be categorised as a public undertaking, as it will be operating in the utility sector, the Borrower would be subject to public procurement and its procurement procedures would need to be in line with the relevant applicable EU procurement legislation (Directives 2014/23/EU and/or 2014/25/EU, where applicable, as well as Directive 92/13/EEC), as transposed in the national legislation, with publication of the tender and award notices in the Official Journal of the European Union, as and where required.
Projektstatus
Genehmigt - 11/12/2024
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).