Signature(s)
Summary sheet
- Solid waste - Water supply; sewerage, waste management and remediation activities
Construction, operation and maintenance of an energy-from-waste (EfW) combined heat and power (CHP) plant in Cardiff, Wales.
The project aims to construct and operate a waste incinerator (Energy from Waste (EfW) plant) in Cardiff, Wales, UK.
The project concerns the construction of a waste incinerator (Energy from waste (EfW)) plant processing more than 100 t/day of residual waste from five authorities in Wales. Hence the project is subject to Annex I of the Environmental Impact Assessment (EIA) Directive 2011/92/EC. An environmental permit has been granted for the site. An integral permit according to the Industrial Emissions Directive (2010/75/EU) will be required by the competent authorities before the plant is put into operation.
The Bank will require the promoter to ensure that contracts for the implementation of the project have been/shall be tendered in accordance with the relevant applicable EU procurement legislation (2004/17/EC/ or 2004/18/EC and 2007/66/EC), with publication of tender notices in the EU Official Journal, as and where appropriate.
Disclaimer
Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).
Documents
News & Stories
General enquiries and comments
The EIB is committed to open communication and encourages constructive stakeholder input regarding its activities.
Enquiries and comments concerning the EIB’s involvement in a project or the financing facilities, activities, organisation and objectives of the EIB, can be sent to the EIB Infodesk.
Alternatively, the EIB can be contacted through its external offices.
Queries regarding details of a specific project, in particular when it is under appraisal by the EIB, should preferably be addressed directly to project promoters.
Media enquiries
Media-related enquiries can be addressed to the EIB Press Office. Please also visit our Media information section.
Complaints mechanism
Any complaint regarding alleged maladministration can be lodged via the EIB Complaints Mechanism. The European Ombudsman acts as an independent external accountability mechanism of the EIB.
Zero tolerance against fraud and corruption
The EIB has a zero tolerance policy on fraud or corruption. To report allegations of fraud and corruption relating to EIB-financed projects, please contact the Fraud and Investigation division. All complaints will be treated as strictly confidential and handled in line with the EIB investigation procedures and the Anti-Fraud Policy.
Related publications