The project will finance a new hot stove for the existing integrated steel plant's blast furnace A, as well as the integration of a heating station in the steel shop.
The project comprises the promoter's capital expenditures related to the installation of new key equipment. This will lead to a significant increase in energy efficiency, entail a considerable reduction of CO2 emissions and increase the consumption of secondary instead of primary raw material. Both investments will lead to more efficient iron and steelmaking and will help to strengthen the promoter's competitiveness.
The installation of such new key equipment represents a change inside an integrated steelworks and thus may fall under Annexe II of the EIA directive. In such a case the local competent authorities will have to establish if a new EIA is required. The Bank's services will establish during the due diligence of the project whether a new EIA is required, as well as appraise any other environmental details.
The promoter has been assessed by the EIB as being a private company not being subject to EU rules on public procurement or concessions. However, if after the project appraisal, the EIB were to conclude that the promoter is after all subject to EU public procurement legislation (i.e. Directive 2014/24/EU), then the Bank would require the promoter to ensure that contracts for the implementation of the project will be tendered in accordance with the relevant applicable EU procurement legislation (2014/24/EU, where applicable, as well as Directive 92/13/EEC), as interpreted by the Court of Justice of the EU, with publication of tender notices in the Official Journal of the European Union, as and where required.
Disclaimer
Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).
Documents
News & Stories
General enquiries and comments
The EIB is committed to open communication and encourages constructive stakeholder input regarding its activities.
Enquiries and comments concerning the EIB’s involvement in a project or the financing facilities, activities, organisation and objectives of the EIB, can be sent to the EIB Infodesk.
Alternatively, the EIB can be contacted through its external offices.
Queries regarding details of a specific project, in particular when it is under appraisal by the EIB, should preferably be addressed directly to project promoters.
Media enquiries
Media-related enquiries can be addressed to the EIB Press Office. Please also visit our Media information section.
Complaints mechanism
Any complaint regarding alleged maladministration can be lodged via the EIB Complaints Mechanism. The European Ombudsman acts as an independent external accountability mechanism of the EIB.
Zero tolerance against fraud and corruption
The EIB has a zero tolerance policy on fraud or corruption. To report allegations of fraud and corruption relating to EIB-financed projects, please contact the Fraud and Investigation division. All complaints will be treated as strictly confidential and handled in line with the EIB investigation procedures and the Anti-Fraud Policy.
Related publications