The project concerns the modernisation and expansion of the existing pulp mill in Figueira da Foz to increase its efficiency and production.
The mill upgrading aims at the removal of efficiency and quality process bottlenecks that will allow a nominal pulp production capacity increase of 70 000 tpa. The upgrading process is expected to improve the emission abatement systems to fully align the plant with the specifications established in the Best Available Techniques (BAT) reference document for the pulp and paper industry. The project will result in increased overall resource efficiency and competitiveness of the company's production site, which is located in a less developed region of the EU. The wood feedstock shall be sourced from sustainably-managed forests that are certified by or aligned with international forest certification standards, either 100% or mixed PEFC/FSC certified wood or FSC controlled wood.
The mill is partially aligned with the Industrial Emissions Directive IED 2010/75 EU. The competent environmental authorities have screened out the project and no new Environmental Impact Assessment (EIA) has been required, since the modernisation process does not constitute a significant change of the installation in terms defined in the IED Directive.
The promoter has been assessed by the EIB as being a private company not being subject to EU rules on public procurement or concessions. However, if after the project appraisal, the EIB were to conclude that the promoter is after all subject to EU public procurement legislation [Directive 2014/23/EU / 2014/24/EU / 2014/25/EU, where applicable], then the Bank would require the promoter to ensure that contracts for the implementation of the project will be tendered in accordance with the relevant applicable EU procurement legislation [Directive 2014/23/EU / 2014/24/EU / 2014/25/EU, where applicable, as well as Directive 92/13/EEC or Directive 89/665/EEC] as interpreted by the Court of Justice of the EU, with publication of tender notices in the Official Journal of the European Union, as and where required.
Disclaimer
Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).
Documents
News & Stories
Photogallery
General enquiries and comments
The EIB is committed to open communication and encourages constructive stakeholder input regarding its activities.
Enquiries and comments concerning the EIB’s involvement in a project or the financing facilities, activities, organisation and objectives of the EIB, can be sent to the EIB Infodesk.
Alternatively, the EIB can be contacted through its external offices.
Queries regarding details of a specific project, in particular when it is under appraisal by the EIB, should preferably be addressed directly to project promoters.
Media enquiries
Media-related enquiries can be addressed to the EIB Press Office. Please also visit our Media information section.
Complaints mechanism
Any complaint regarding alleged maladministration can be lodged via the EIB Complaints Mechanism. The European Ombudsman acts as an independent external accountability mechanism of the EIB.
Zero tolerance against fraud and corruption
The EIB has a zero tolerance policy on fraud or corruption. To report allegations of fraud and corruption relating to EIB-financed projects, please contact the Fraud and Investigation division. All complaints will be treated as strictly confidential and handled in line with the EIB investigation procedures and the Anti-Fraud Policy.
Related publications