Countries
Sector(s)
Jordan : € 81,250,000
Water, sewerage : € 81,250,000
Signature date(s)
27/10/2019 : € 16,250,000
5/03/2019 : € 65,000,000
(*) Including a € 6,987,500 Investment Grants provided by the ECONOMIC RESILIENCE INITIATIVE FUND ,a € 325,000 Investment Grants provided by the ECONOMIC RESILIENCE INITIATIVE FUND
Link to source

Summary sheet

Release date
5 November 2018
Status
Reference
Signed | 05/03/2019
20180058
Project name
Promoter - financial intermediary
DEIR ALLA WATER SUPPLY AND SANITATION
MINISTRY OF WATER AND IRRIGATION - HASHEMITE KINGDOM OF JORDAN
Proposed EIB finance (Approximate amount)
Total cost (Approximate amount)
EUR 81 million
EUR 97 million
Location
Sector(s)
  • Water, sewerage - Water supply; sewerage, waste management and remediation activities
Description
Objectives

The project will improve the existing water supply systems of the Deir Alla and Al Karameh districts in the Jordan Valley. It will also provide for the first time a centralised wastewater collection and treatment system for Deir Alla.

The overall long-term objectives of the project are to contribute to: (i) Improvement of potable water quality in the project area; (ii) Mitigating climate change impact by minimising water losses through leakages and thus a reduction of non-revenue water; (iii) Reduced energy consumption in the water supply system through increased energy efficiency and reduced leakages of the water supply system; (iv) Improvement of the groundwater quality; (v) Improvement in security of water supply for agriculture by providing an additional source of water and thus mitigating climate change impact; (vi) Job creation, during construction and operation, in one of the poorest areas of Jordan; and (vii) Institutional strengthening of the beneficiary. The project is a high priority for the Jordanian government under the National Water Strategy 2016-2025, and is fully in line with EU-Jordan Partnership Priorities, especially the objectives of fostering Growth and Job Opportunities. The project is fully in line with EIB's objectives under the External Lending Mandate 2014-2020, specifically the development of social and economic infrastructure, as well as the Bank's recently adopted Water Sector Lending Orientation. Finally, the project is also in line with UN Sustainable Development Goals #6, which calls for ensuring availability and sustainable management of water and sanitation for all and # 11 (make cities and human settlements inclusive, safe, resilient and sustainable).

Environmental aspects
Procurement

The project will have a positive impact on public health and the environment by reducing the discharge of untreated waste water to the Jordan Valley. Inside the EU, the project components would be categorised under Annex II and therefore would be subject to environmental screening to define if an Environmental Impact Assessment (EIA) would be required according to the relevant competent authority. Climate change aspects will be examined during the appraisal. The Bank will assess the social aspects of the project during appraisal to ensure adherence to its social standards.

The promoter will have to ensure that implementation of the project will be done in accordance with EIB's Guide to Procurement.

Under ELM Guarantee
Comments

This operation is covered by the ELM Guarantee.

Total financing for the project amounts EUR 81m, consisting of about EUR 65m of EIB loan and about EUR 16m of a an Economic Resilience Initiative (ERI) investment grant.

Link to source

Disclaimer

Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).

Documents

Environmental and Social Impact Assessment (ESIA) - DEIR ALLA WATER SUPPLY AND SANITATION - Environmental and Social Assessment for the Feasibility Study
Publication Date
7 Nov 2018
Document language
Main Topic
Lending
Document Number
88030245
Document Focus
Environmental Information
Project Number
20180058
Sector(s)
Countries
Publicly available
Download now
Environmental and Social Data Sheet (ESDS) - DEIR ALLA WATER SUPPLY AND SANITATION
Publication Date
16 Jan 2019
Document language
Main Topic
Lending
Document Number
87806978
Document Focus
Environmental Information
Project Number
20180058
Sector(s)
Countries
Publicly available
Download now

News & Stories

Photogallery

General enquiries and comments

The EIB is committed to open communication and encourages constructive stakeholder input regarding its activities.
Enquiries and comments concerning the EIB’s involvement in a project or the financing facilities, activities, organisation and objectives of the EIB, can be sent to the EIB Infodesk.
Alternatively, the EIB can be contacted through its external offices.
Queries regarding details of a specific project, in particular when it is under appraisal by the EIB, should preferably be addressed directly to project promoters.

Media enquiries

Media-related enquiries can be addressed to the EIB Press Office. Please also visit our Media information section.

Complaints mechanism

Any complaint regarding alleged maladministration can be lodged via the EIB Complaints Mechanism. The European Ombudsman acts as an independent external accountability mechanism of the EIB.

Zero tolerance against fraud and corruption

The EIB has a zero tolerance policy on fraud or corruption. To report allegations of fraud and corruption relating to EIB-financed projects, please contact the Fraud and Investigation division. All complaints will be treated as strictly confidential and handled in line with the EIB investigation procedures and the Anti-Fraud Policy.

Related publications