Reference: 20140502
Release date: 3 September 2015

Promoter – Financial Intermediary

NEOEN

Location

Description

Construction of a set of 25 projects of 12 MW, totaling 300MW. The project is located in the town of Cestas, in the Aquitaine region.

Objectives

The project contributes to national and European targets for renewable energy production and thus to European Union objectives in terms of action against climate change and for the security and sustainability of energy supply.

Comments

Sector(s)

  • Energy - Electricity, gas, steam and air conditioning supply

Proposed EIB finance (Approximate amount)

EUR 56 million

Total cost (Approximate amount)

EUR 352 million

Environmental aspects

The project is expected to have limited environmental impact during construction and operation. An environmental impact assessment (EIA) has been performed. The Bank will review the EIA during appraisal, including a verification of compliance with national and EU environmental and biodiversity regulations.

Procurement

The promoter is a private company not operating in the utilities sector and in principle not having the status of a contracting authority. It would thus not be covered by EU directives on procurement.

Status

Approved - 2/10/2015

Disclaimer

Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).

Related tags

France Energy