    Reference: 20040459
    Release date: 21 December 2005

    Promoter – Financial Intermediary

    Elia System Operator SA

    Location

    Description

    Upgrade and reinforcement of the high-voltage electricity grid in Belgium.

    Objectives

    By maintaining an adequate and cost-effective supply of electricity, the project would contribute to the rational use of energy and is expected to support the economic development in Belgium and its neighbouring countries.

    Comments

    Electricity transmission.

    Sector(s)

    Proposed EIB finance (Approximate amount)

    Approx. EUR 125 million.

    Total cost (Approximate amount)

    Approx. EUR 270 million.

    Environmental aspects

    Belgian legislation does not require an EIA for reinforcing the existing overhead transmission lines included in this project. Other project components do not fall under EIA directive.

    Procurement

    The promoter has confirmed that their procurement rules are fully in line with the EU public procurement procedures (Utilities Directive 93/38/EC pending transposition of 2004/17/EC) and include publication in the OJEU.

    Status

    Signed - 19/12/2005

    Disclaimer

    Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
    They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).

    Related tags

    Belgium Energy