Reference: 20090447
Release date: 6 August 2009

Promoter – Financial Intermediary

Private/Disitribution System Operator in Poland

Location

Description

The project comprises a large number schemes for extending and modernising the promoter’s electricity networks covering the investment period 2009-2011.

Objectives

The project includes the construction and refurbishment of 1,300 km of MV lines, 3,100 km of LV lines and around 2,600 MV/LV substations as well as few HV lines for the connection of renewable energy sources, mainly wind farms.

Sector(s)

Proposed EIB finance (Approximate amount)

EUR 200 million.

Total cost (Approximate amount)

EUR 572 million.

Environmental aspects

All the projects schemes will fall under Annex II of the EIA directive, leaving it to the national competent authority to decide whether an EIA will be required in line with screening criteria specified in the directive. The criteria applied by the national competent authorities in Poland will be investigated during the appraisal. In line with the Bank guidelines the evaluation will assess the promoter’s capacity to address environmental and biodiversity issues in an appropriate way.

Procurement

The promoter follows public procurement procedures in compliance with the Directive 2004/17/EC and with the Polish Public Procurement Act. The promoter’s approach for the procurement of works, goods and services will be further evaluated during the appraisal.

Status

Signed - 16/12/2009

Disclaimer

Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.